The satellite was planned to be launched from Sriharikota on December 20 at 4:01 pm and the 29 hour-countdown sequence was scheduled to commence at 11 am on Sunday. But due to the leak in the cryogenic engine, the Launch Authorisation Board, which met today to review the results of pre-countdown checks, did not authorise it, he said. The revised schedule for the launch would be firmed up after ascertaining the cause for the leak, remedial actions and due verifications, he added. The rocket, seventh mission of GSLV-FO6, has major changes incorporated as compared to the previous flights. It includes loading 15 tonnes of propellants in its third stage of flight and uprating of the third stage thrust by 26 per cent, ISRO said.